Gravel Calculator

Last Updated:

Work out how much gravel or sand to order for a driveway, path, drain or base, in cubic yards, tons and tonnes, with compaction and waste. Free, no sign-up.

Quick answer: Gravel weighs about 1.42 short tons per cubic yard on the New Mexico state conversion table. Multiply length by width in feet and depth in inches, divide by 12 and then by 27 for cubic yards, then multiply by 1.42 for tons. A 20 ft by 10 ft pad 4 inches deep is 2.47 cubic yards, about 3.5 tons, before any compaction allowance.

Gravel and sand calculator

Short tons per cubic yard, from the table below
Sets every length, area and depth field
Split an odd shape into rectangles and run each
ft
Required
ft
Required
in
Finished depth after compaction. Required
%
Optional. Share of the loose volume lost when it packs down
%
Optional. Added on top of the order
Optional. Any currency, delivery not included

Enter the size of the area and the depth above to see your result.

Gravel to order

—

Cubic yards—
Cubic metres—
Short tons (2,000 lb)—
Metric tonnes—
Cost—
Density used—

The same area at other depths, with your allowances
DepthCubic yardsShort tonsTonnes

📐 The gravel formula

Cubic yards = length (ft) × width (ft) × depth (in) ÷ 12 ÷ 27. Short tons = cubic yards × tons per cubic yard. With shrinkage c and waste w, order = finished volume ÷ (1 − c) × (1 + w). In metric, cubic metres = length (m) × width (m) × depth (cm) ÷ 100, and tonnes = short tons × 0.9072.

How to use the gravel calculator

1

Pick the material

Choose gravel, pit-run gravel, base course, sand or riprap. Each carries a weight in short tons per cubic yard. If your supplier quotes a weight, pick Custom density and type theirs in.

2

Set the units and the shape

Choose feet and inches or metres and centimetres, then Rectangle, Circle or I know the area. Every length field relabels itself to match.

3

Enter the size and the depth

Type the length and width, the diameter, or the area. Then type the finished depth, in inches or centimetres. A 4-inch layer is 4, not 0.33.

4

Add your allowances

Fill in the compaction shrinkage if the material will be packed down, and a spill and waste percentage if you want a buffer. Both are optional and start blank.

5

Read the order

The big figure is the weight to order. The tiles show cubic yards, cubic metres, short tons and metric tonnes, and the table shows the same area at other depths.

How many tons of gravel do I need?

Work out the volume first, then turn it into weight. For a rectangle, multiply length by width in feet to get square feet. Multiply that by the depth in inches and divide by 12 to get cubic feet. Divide by 27 to get cubic yards, then multiply by the tons per cubic yard for your material.

A homeowner topping up a 20 ft by 10 ft parking pad with 4 inches of gravel has 200 square feet. At 4 inches that is 200 × 4 ÷ 12 = 66.7 cubic feet, or 2.47 cubic yards. At 1.42 tons per cubic yard the pad takes 3.51 tons. Put 15% for compaction in the calculator and the order rises to 4.12 tons, because the loose gravel will pack down to the 4 inches you want.

Do the sum for each separate area and add the tons. A path and a pad are two jobs, not one.

How much does a cubic yard of gravel weigh?

The calculator uses the conversion factors the New Mexico Energy, Minerals and Natural Resources Department publishes for reporting construction materials (read on November 23, 2026), adapted from a federal Bureau of Land Management handbook. One cubic yard of gravel between 1/4 and 2 inches is 1.42 short tons, about 2,840 pounds.

Short tons per cubic yard, as used here (New Mexico EMNRD conversion factors)
MaterialShort tons per cubic yardPounds per cubic yardKilograms per cubic metre
Gravel, 1/4 to 2 inch1.422,8401,685
Pit-run gravel1.623,2401,922
Base course1.252,5001,483
Sand1.452,9001,721
Riprap or gabion stone1.052,1001,246

Treat these as a solid starting point, not a promise. Rock type, stone size, how much fine material is mixed in and how wet the pile is all move the real weight. Pit-run gravel carries a lot of sand and fines, which is why it weighs more than clean gravel. If your supplier gives you a weight per yard, choose Custom density and use theirs.

Moisture matters most with sand. Damp or wet sand weighs more than dry sand, and the truck scale ticket records the load as delivered. We have not published a wet-sand figure because the sources we read do not give one. If your ticket runs heavier than the estimate on a rainy week, that is the likely reason.

Gravel is sold by the ton or by the yard: which should I order?

Many quarries sell gravel by weight, because they load trucks across a truck scale. Landscape yards and garden centers often sell it by the cubic yard, and bagged gravel is sold by the cubic foot or by weight. Ask which unit the quote uses before you compare prices. A price per ton and a price per yard are not the same number, and at 1.42 tons per yard a $45 ton is about $64 a yard.

The calculator gives you both, so you can order in whichever unit the supplier works in. If you want the price comparison done for you, enter a price per ton and the cost tile shows the total for the order. Delivery is almost always extra.

Do I need extra gravel for compaction?

Yes, if the gravel will be packed down. Gravel dumped from a truck is loose, and it shrinks as it settles and is rolled. The Federal Highway Administration's 2015 guide to gravel roads warns that ordinary compaction on a road can cut the volume by 30 percent or more, and says the quantity should be worked out with that shrinkage in mind (section 3.19).

The calculator treats shrinkage the way it actually works. If 30% of the loose volume is lost, you need to order the finished volume divided by 0.70, which is 43% more, not 30% more. Enter 30 and a 2.47 cubic yard job becomes 3.53 cubic yards. A light pad that is raked and tamped by hand loses far less, which is why the box starts blank and the placeholder shows 15.

Spill and waste is separate. It covers what lands on the grass, what stays in the wheelbarrow and what the truck leaves behind. Five percent is a common buffer for a small job. That figure is common practice, not a published rule.

How deep should gravel be?

It depends on the job, and the figures below are common practice, not a standard. For road-style gravel, the 2015 FHWA guide gives one firm rule: a layer should be at least twice the thickness of the largest stone in it, and at least 2 inches (section 3.21). A mix with 1 inch top-size stone therefore needs at least 2 inches, and a mix with 1.5 inch stone needs 3.

Typical finished depths by job (common practice, not a standard)
JobTypical depthWhat decides it
Garden path or mulch-style cover2 to 3 inchesFoot traffic only
Driveway surface layer4 to 6 inchesVehicle weight and the base underneath
Base under pavers or a shed4 to 6 inchesSoil type and the load above
French drain trench12 to 24 inchesTrench depth and where the pipe sits
Retaining wall backfill12 inches behind the wallWall height and the drainage plan

Check the local rules for anything structural. A retaining wall, a drain that carries water away from a foundation and a driveway that takes heavy trucks are all jobs where the engineer or the building authority sets the depth, not a calculator.

How much gravel covers 100 square feet?

A 100 square foot area takes 0.62 to 3.70 cubic yards of gravel, or 0.88 to 5.26 tons, at depths from 2 to 12 inches and 1.42 tons per cubic yard. The table shows each depth, so you can sanity-check an order. Scale it up or down: 400 square feet at 4 inches is four times the 4 inch row, which is 4.9 cubic yards and 7.0 tons.

Gravel for 100 square feet at 1.42 tons per cubic yard (our arithmetic)
DepthCubic yardsShort tonsSquare feet per ton
2 inches0.620.88114
3 inches0.931.3176
4 inches1.231.7557
6 inches1.852.6338
8 inches2.473.5129
12 inches3.705.2619

Gravel for a driveway, a French drain or a base under pavers

A driveway is the biggest job most homeowners tackle. A single-car drive 12 feet wide and 40 feet long needs 480 square feet. A 4-inch layer is 160 cubic feet, or 5.93 cubic yards, about 8.4 tons at 1.42, before any compaction allowance. A new drive on soft ground usually needs a deeper base of coarser stone under a finer top layer, so run the calculator once for each layer. A concrete driveway or slab base is also gravel: run this calculator for the base, commonly 4 inches (common practice), and the concrete calculator for the slab.

A French drain is a trench filled with gravel around a perforated pipe. A trench 50 feet long, 1 foot wide and 18 inches deep holds 75 cubic feet, or 2.78 cubic yards, about 3.94 tons of gravel. Treat that as the stone volume only, because the pipe and any fabric take up room and the trench rarely stays a perfect rectangle.

A base under pavers or a shed pad is one rectangle at the depth the paver maker specifies. Our paving calculator covers the pavers and the bedding sand, and this calculator covers the stone base beneath them.

Gravel calculator in metres and tonnes (UK, Australia and Canada)

Switch the units to metres and centimetres and the fields become length and width in metres, area in square metres (m²) and depth in centimetres. The answer comes back in cubic metres (m³) and metric tonnes as well as cubic yards and short tons.

The two tons are different weights. A US short ton is 2,000 pounds, or 907 kilograms. A metric tonne is 1,000 kilograms. An order for 10 short tons is 9.07 tonnes. If a supplier quotes a price per ton in a metric country, they almost always mean the metric tonne, but ask. The calculator shows both so you can match the quote.

To use your own density in metric mode, type it in kilograms per cubic metre. The gravel row works out at about 1,685 kg/m³ and sand at about 1,721 kg/m³.

Common mistakes with gravel quantities

Entering the depth in feet is the first one. A 4-inch layer is 4 in the depth field, not 0.33 or 0.4, because the field takes inches. The second is mixing short tons and metric tonnes when comparing quotes. The third is ordering the finished volume when the gravel will compact, which leaves the job a few inches short.

The fourth is treating a sloped or uneven surface as flat. Measure the average depth, not the shallow end. The fifth is forgetting that a first layer sinks into soft ground. A geotextile fabric under the stone stops that and is worth pricing before you order.

Finally, remember that estimates round. Order a little over, because a half-load short is worse than a half-load spare.

⚠️ Disclaimer This calculator gives estimates from published average weights as read on November 23, 2026. Real gravel varies with rock type, size, moisture and how it is placed, and suppliers sell by their own measure. It does not size a structural base, a drain or a retaining wall. Confirm quantities and depths with your supplier and, where a job carries load or water, with an engineer or your local building authority.

Frequently Asked Questions

Gravel from 1/4 to 2 inches weighs about 1.42 short tons per cubic yard, or roughly 2,840 pounds, on the New Mexico state conversion table (read November 23, 2026). A handy check: one cubic yard covers 81 square feet at 4 inches deep, which is about 57 square feet per ton. Your supplier's weight governs, so use the Custom density option if you have it.
Multiply length by width, then by the depth in inches, then divide by 12 and 27. A long rural lane 10 ft wide and 60 ft long at 6 inches deep is 600 square feet, which takes 11.11 cubic yards, about 15.8 tons at 1.42 tons per yard. Most drives have a base layer and a top layer, so run the calculator once for each and add the two.
Both, so convert before you compare. Say one supplier quotes $45 a ton and another quotes $60 a cubic yard. At 1.42 tons per yard the first works out at $63.90 a yard, so the second is about $3.90 a yard cheaper before delivery. Enter a price per ton in the calculator and the cost tile does the sum for your whole order.
Divide, do not add. A common slip is to add the shrinkage percentage, so 30% becomes 1.30 times the volume. The right factor is 1 divided by 0.70, which is 1.43. On a 5 cubic yard finished job that is 7.14 cubic yards ordered, not 6.50, and the gap is the difference between filling the job and finishing a few inches short. A hand-tamped path loses much less, so enter your own figure.
Width is the number people guess. A trench 100 feet long, 8 inches wide and 2 feet deep holds 4.94 cubic yards, about 7.0 tons. In the calculator, pick I know the area, enter 66.7 square feet (100 feet by 8 inches) and a depth of 24 inches. The pipe takes up some room, so treat the result as the upper figure.
Pick Sand in the material list and enter the area and depth. A 10 ft by 10 ft sandbox filled 6 inches deep takes 1.85 cubic yards, about 2.7 tons at 1.45 short tons per cubic yard. That makes sand slightly heavier than clean gravel at 1.42, so do not reuse a gravel tonnage for a sand order.
Start with the gravel row for the weight, then check it against your supplier. A graded crushed stone such as No. 57 can weigh more or less than 1.42 tons a yard. Choose Custom density and type the supplier's figure. The volume math does not change.
A short ton is 2,000 pounds, used in the United States. A metric tonne is 1,000 kilograms, so one short ton is 0.907 tonnes. Convert before you compare quotes: a price of 50 per tonne is 45.36 per short ton. The calculator shows both weights for the same order, so you can match whichever unit your supplier uses.

Sources & Methodology

The weights, the compaction guidance and the layer rule on this page come from these publications, read on November 23, 2026:

Volume is length × width × depth, with 1 yard = 0.9144 m, so 1 cubic yard = 0.7646 cubic metres, and a short ton is 2,000 pounds = 907.18 kg. Compaction shrinkage c raises the order by dividing by (1 − c), and spill and waste w multiplies it by (1 + w). Tons are cubic yards × tons per cubic yard. The depth guide is common practice, and the 5% spill figure is our estimate. Figures are rounded to two decimals.