Work out how many tons of asphalt a driveway or paved area needs, from square feet or square yards and thickness. Short tons and metric tons, with waste and cost. Free, no sign-up.
Quick answer: Hot mix asphalt weighs about 110 pounds per square yard for every inch of thickness, inside a published range of 108 to 120 (Penn State 2025 handout, from the Pennsylvania Asphalt Pavement Association checklist). Multiply square yards by thickness in inches by 110, then divide by 2,000 for short tons. A 12 ft by 40 ft driveway at 2 inches is 53.3 square yards, which takes about 5.9 tons before any waste.
Asphalt and driveway tonnage calculator
Enter your figures above to see your result.
Asphalt to order
—
| Inches | Short tons | Metric tons | ft² per ton |
|---|
📐 The asphalt tonnage formula
Short tons = square yards × thickness (in) × pounds per square yard per inch ÷ 2,000. Square yards = square feet ÷ 9. A mix at 146.7 pounds per cubic foot is 110 pounds per square yard per inch, because pounds per cubic foot × 0.75 gives that figure. With waste w, order = tons × (1 + w). In metric, metric tons = area (m²) × thickness (cm) ÷ 100 × density (kg/m³) ÷ 1,000.
How to use the asphalt calculator
Pick the mix weight
Choose Typical hot mix at 110 pounds, Lighter at 108 or Heavier at 120. If you have the mix design, choose I have the mix design and enter its maximum density and the in-place percentage. For a supplier's own weight pick Custom density.
Set the units and the shape
Choose feet and inches or meters and centimeters, then Rectangle, Circle or I know the area. In area mode you can enter square feet or square yards.
Enter the size and the thickness
Type the length and width, the diameter or the area. Then type the finished thickness after rolling, in inches or centimeters. A 2-inch layer is 2, not 0.17.
Add a waste allowance and a price
Fill in a waste percentage if you want a buffer, and a price per ton or metric ton if you want a material cost. Both are optional and start blank.
Read the order
The big figure is the weight to order. The tiles show short tons, metric tons, square yards, volume and cost, and the table shows the same area at other thicknesses with the coverage of one ton.
How many tons of asphalt do I need?
Whether you call it an asphalt tonnage calculator or an asphalt driveway calculator, the sum is the same. Work out the area in square yards, multiply by the thickness in inches, then multiply by the weight of one square yard of mix per inch. The plant sells by weight, so the last step is dividing pounds by 2,000. The calculator does all of it, and asking for square feet or square yards is the same sum with a divide-by-nine in front.
Take a single-car driveway 12 feet wide and 40 feet long. That is 480 square feet, or 53.3 square yards. Paved 2 inches thick at 110 pounds per square yard per inch, the job weighs 53.3 × 2 × 110 = 11,733 pounds, which is 5.87 tons. Add 5% for waste and you order 6.16 tons. A two-car apron 20 feet by 40 feet at 3 inches is 88.9 square yards and 14.67 tons.
Round shapes work the same way. A turnaround 20 feet across has an area of 314 square feet, and at 3 inches it takes 5.76 tons. Run each separate area on its own and add the tons, because a drive and a pad are two jobs.
How much does asphalt weigh per square yard and per inch?
A typical compacted hot mix weighs 108 to 120 pounds per square yard for every inch of thickness. That is 144 to 160 pounds per cubic foot. The Northeast Center of Excellence for Paving Technology at Penn State prints the range in its 2025 field handout, from the Pennsylvania Asphalt Pavement Association's quality checklist (read November 24, 2026). It adds that the weight changes with the aggregate, the binder content and the density the roller reaches.
| Mix | Pounds per yd² per inch | Pounds per cubic foot | Kilograms per cubic meter |
|---|---|---|---|
| Lighter hot mix | 108 | 144.0 | 2,307 |
| Typical hot mix | 110 | 146.7 | 2,349 |
| Heavier hot mix | 120 | 160.0 | 2,563 |
The 110 is the middle choice because it is the figure the handout works through. The example takes a mix with a maximum density of 156 pounds per cubic foot, multiplies by 0.75 to get pounds per square yard per inch, then by 94% for the density reached in place, and lands on 110. So 110 is a typical value inside the published range, not a law of nature. Your supplier's job mix formula has the real number for your mix.
The same arithmetic runs the other way. Choose I have the mix design, type the maximum density and the in-place percentage, and the calculator applies the handout's method. A mix at 156 pounds per cubic foot and 92% in place weighs 107.6 pounds per square yard per inch, which is about 2% lighter than the typical figure on the 12 by 40 foot driveway at 2 inches.
Why is there no compaction box?
There is no compaction box because the weights above are already for compacted asphalt in place, and rolling a mat does not change how much it weighs. A paver lays the mix thicker than the finished layer and the rollers press it down to the thickness on the plans. The tons that left the plant are the tons that stay on the ground. You type the finished thickness, and the weight follows from it.
That is different from loose stone, where the pile shrinks as it settles and the order has to be bigger than the finished volume. Our gravel calculator does allow for that shrinkage, and copying that habit to asphalt inflates the order for nothing. If you want a buffer, use the waste box. It covers the ragged edge, an uneven base that takes more mix than the drawing assumed and the last load that is never quite measured to the shovel. Five percent is our estimate for a small job, not a published figure.
How thick should an asphalt driveway be?
Two published design guides give figures to work from. The Ontario Hot Mix Producers Association's 2004 driveway guide sets 2 inches (50 mm) of compacted hot mix as the minimum for a driveway, and for a more durable one it describes a 2-inch base course with a 1.5-inch surface course on top, which adds up to 3.5 inches. The Wisconsin Asphalt Pavement Association's 2018 parking lot design guide puts driveways, sidewalks and parking lots under 50 stalls at 3 inches of asphalt on good subgrade soil, 3.5 on medium and 4 on poor, over 6 to 12 inches of compacted aggregate base. Both are regional design guides, not national standards, so ask the contractor who will do the work. If the drive is pavers instead, the paving calculator covers the surface and the gravel calculator sizes the base. A concrete drive is the concrete calculator.
| Job | Thickness | Source |
|---|---|---|
| Walkway or patch | 1.5 to 2 inches | Common practice, no guide read |
| Driveway, minimum | 2 inches (50 mm) | Ontario Hot Mix Producers Association, 2004 |
| Durable driveway | 3.5 inches: 2-inch base course plus 1.5-inch surface course | Ontario Hot Mix Producers Association, 2004 (the 3.5 is our sum of the two courses) |
| Lot under 50 stalls | 3 inches on good subgrade, 3.5 on medium, 4 on poor | Wisconsin Asphalt Pavement Association, Table 3.1 (also driveways and sidewalks) |
| Lot of 50+ stalls | 3 to 3.5 inches on good subgrade, 3.5 to 4 on medium, 4 to 4.5 on poor | Wisconsin Asphalt Pavement Association, Table 3.2 |
A thickness is not the whole design. Asphalt over a weak base cracks whatever the tonnage, so a calculator can tell you how much to buy but not whether the layer is enough.
How many square feet does a ton of asphalt cover?
At 110 pounds per square yard per inch, a ton covers about 82 square feet at 2 inches, and the coverage falls in step with the thickness. One ton at 1 inch covers 164 square feet, and the table shows the other depths. The last column turns it round: a 1,000 square foot area takes 12.2 tons at 2 inches.
| Thickness | Square feet per ton | Square yards per ton | Tons per 1,000 square feet |
|---|---|---|---|
| 1 inch | 163.6 | 18.2 | 6.11 |
| 1.5 inches | 109.1 | 12.1 | 9.17 |
| 2 inches | 81.8 | 9.1 | 12.22 |
| 2.5 inches | 65.5 | 7.3 | 15.28 |
| 3 inches | 54.5 | 6.1 | 18.33 |
| 4 inches | 40.9 | 4.5 | 24.44 |
How do I convert square feet or square yards to tons of asphalt?
Square feet to tons: divide by 9 for square yards, multiply by the thickness in inches and by 110, then divide by 2,000. Square yards to tons skips the first step. A shortcut at 110 pounds is tons = square feet × thickness ÷ 163.6, so 1,000 square feet at 2 inches is 1,000 × 2 ÷ 163.6 = 12.2 tons.
The handout's own worked example is a parking lot 150 feet by 300 feet with a 3-inch compacted layer. That is 5,000 square yards, 1,650,000 pounds and 825 tons. It is a good test of the calculator: enter 300 and 150 for the sides and 3 for the thickness and you get 825 tons. The same handout shows a 22-ton truckload covering about 150 feet of a 12-foot lane at 2 inches.
Using the asphalt calculator in the US, UK, Australia and Canada
In the US, the calculator's default mode works in feet, inches, square yards and short tons. In the UK, Australia and Canada, switch the units to metres and centimetres. Length and width are in metres, area in square metres and thickness in centimetres, and the order comes back in metric tonnes as well as short tons. A 12 metre by 5 metre drive at 5 centimetres is 60 square metres and 3 cubic metres, which weighs about 7.05 tonnes at 2,349 kilograms per cubic metre. That is 7.77 short tons.
In the UK the same material is often called tarmac, and in the US many people say blacktop. They are all hot mix asphalt for the purposes of weight. Suppliers outside the US quote tonnes, so check which ton is on the quote before you compare prices. The price field becomes a price per tonne in metric mode, and it takes any currency, so type pounds, Australian dollars or Canadian dollars as the quote reads. The weights come from a Pennsylvania document, so treat them as a starting estimate and use the density your own plant or road authority publishes.
What about cold patch, bagged asphalt and millings?
This calculator is for hot mix laid by a paving crew, so it does not guess at a weight for bagged cold patch or recycled millings. Cold patch is sold in bags with the coverage printed on them, and that figure beats anything we could estimate. For a driveway of loose millings, pick Custom density and type your supplier's weight. The area and thickness arithmetic is identical.
What does an asphalt driveway cost?
The price field here is for the material only. Enter the plant's price per ton and the cost tile multiplies it by the tons to order. A contractor's quote is usually per square foot or per job and includes the base, the equipment, the labor and the delivery, so it will run higher than a material-only figure and should not be compared with it directly. Ask for the thickness, the tonnage and the base work in writing.
Common mistakes with asphalt quantities
Entering the thickness in feet is the first. A 2-inch layer is 2 in the thickness field, not 0.17. The second is adding a compaction percentage when the weight is already for compacted mix. The third is mixing short tons and metric tons when comparing quotes.
Next comes measuring a driveway as a rectangle when it flares at the road or curves around a garden. Split it into shapes, run each and add them. And a thickness is the average, so if the base is dished or uneven, expect to use more than the calculator says. Order a little over, because running short in the middle of a job is worse than a small surplus.
Frequently Asked Questions
Sources & Methodology
The mix weights and the square-yard conversion on this page come from the Penn State handout, and the thickness figures from the two design guides, all read on November 24, 2026:
- Northeast Center of Excellence for Paving Technology (Penn State): 2025 Field Technician handout, with the Pennsylvania Asphalt Pavement Association's “Constructing Quality Asphalt Pavements in Pennsylvania Checklist”, yield calculations and the note on compacted mix weight
- Ontario Hot Mix Producers Association: The ABCs of Driveways, Issue 1.0, June 2004 (compacted driveway thickness, base and surface course)
- Wisconsin Asphalt Pavement Association: Asphalt Parking Lot Design Guide, version 2018.0 (Tables 3.1 and 3.2, pavement thickness by use and subgrade)
The handout converts pounds per cubic foot to pounds per square yard per inch by multiplying by 0.75, and states that a typical compacted mix weighs 108 to 120 pounds per square yard per inch, or 144 to 160 pounds per cubic foot. Its 110 figure is a worked example (156 pounds per cubic foot at 94 percent in place), so we treat it as a typical value inside that range. Unit conversions use 1 yard = 0.9144 m, 1 inch = 2.54 cm, 1 pound = 0.45359237 kg and a short ton of 2,000 pounds, so 1 short ton = 0.9072 metric tons. The walkway and patch range is common practice, the 5 percent waste figure is our estimate and the price is an illustration. Figures are rounded to two decimals.